- ReferenceZ1032/Bed/5/5
- TitleFifth Progress and Financial report. The report is divided into the following sections 1) Project Control: details on the physical programme which list that severe winter conditions and labour disputes, Railway and National had hampered progress in the first quarter of 1979 2) Progress Report: details on rolling stock 3) Financial Report: costs of works at Harlington and Luton stations 4) Conclusions and Recommendations 5) Appendices: general statement of progress of the resignalling and route improvements
- Date free text16 Jun - 25 Sep 1979
- Production dateFrom: 1979 To: 1979
- ExentNo. of pieces: 1
- Formatsheets of paper
- Level of descriptionitem