    Z1032/Bed/5/7
  • Title
    Seventh Progress and Financial report. The report is divided into the following sections 1) Project Control: 2) Progress Report: details on track rationalisation, route improvements and stations at Leagrave, Bedford and Flitwick 3) Financial Report 4) Conclusions and Recommendations 5) Appendices: includes a general statement of progress which lists how many (Kms) of track realignment has been completed, the amount of bridges to be reconstructed etc